Contracts….Additional Work
Retrofit often involves conditions of poor previous construction
Make clear that owner responsible for work due to unforeseen circumstances:
- If increases scope of work
- If owner request additional work
- If necessitated by hidden pre-existing conditions
Notes:
- Retrofit work often involves conditions of poor previous construction and other circumstances for which the contractor does not want to be responsible.
- Make it clear that the owner is responsible to pay for work due to unforeseen circumstances where:
- It increases the scope of work
- The owner request the additional work be done
- It is necessitated by hidden preexisting conditions